W. Prospect Ave Stormwater Project to begin 5/13

detour plan

As part of the Township's continuing commitment to stormwater management, a project that will help alleviate issues on West Prospect Avenue between Pennsylvania Avenue and Highland Avenue will begin the week of May 13.

Crews will install storm pipe and catch basins on West Prospect Avenue to address stormwater issues, especially in the winter when temperatures drop and runoff can freeze.

Construction will start the week of May 13 and take about two weeks. West Prospect Avenue will be closed from 7 a.m. to 4 p.m. Crews will coordinate access with residents. Highland Avenue will be the detour around the work area. Please use caution when driving in the area.

The work is funded through the Upper Gwynedd Township Capital Fund.