Upper Gwynedd Township's 2023 Road Paving Paving program is scheduled to begin on Monday, May 22, 2023. The program will begin with concrete work on Forrest Lane & in the Rexdale Development. Here is the tentative schedule for the first two weeks of the program:

May 22nd- May 23rd: Forrest Lane ADA ramps
May 24th-26th: Rexdale Development ADA ramps 
May 30th- June 2nd: Rexdale Development ADA ramps 

The contractor will then be moving to the milling & paving of the following streets: South Broad Street, Hancock Road, and & Forrest Lane. We ask that you use caution in these areas while they are working!

Click here to view the full schedule:  https://www.uppergwynedd.org/sites/g/files/vyhlif1351/f/uploads/pmugt025...

Please note that the schedule is tentative, weather permitting, and subject to change.  Stay tuned for updates!